GREAT PLAINS ENERGY INCORPORATED
|
43-1916803
|
||
(A Missouri Corporation)
|
||||
1200 Main Street
|
||||
Kansas City, Missouri 64105
|
||||
(816) 556-2200
|
||||
NOT APPLICABLE
|
||||
(Former name or former address,
if changed since last report)
|
||||
000-51873
|
KANSAS CITY POWER & LIGHT COMPANY
|
44-0308720
|
||
(A Missouri Corporation)
|
||||
1200 Main Street
|
||||
Kansas City, Missouri 64105
|
||||
(816) 556-2200
|
||||
NOT APPLICABLE
|
||||
(Former name or former address,
if changed since last report)
|
[ ]
|
Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
|
[ ]
|
Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
|
[ ]
|
Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act
|
(17 CFR 240.14d-2(b))
|
|
[ ]
|
Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
|
Item 7.01
|
Regulation FD Disclosure
|
Item 9.01
|
Financial Statements and Exhibits
|
(d) Exhibits
|
|
Exhibit No.
|
Description
|
99.1
|
Investor presentation slides
|
GREAT PLAINS ENERGY INCORPORATED
|
|
/s/ Ellen E. Fairchild
|
|
Ellen E. Fairchild
|
|
Vice President, Corporate Secretary and Chief Compliance Officer
|
KANSAS CITY POWER & LIGHT COMPANY
|
||
/s/ Ellen E. Fairchild
|
||
Ellen E. Fairchild
|
||
Vice President, Corporate Secretary and Chief Compliance Officer
|
Exhibit Index
|
|
Exhibit No.
|
Description
|
99.1
|
Investor presentation slides
|
Comprehensive Energy Plan
|
||
|
Project description
|
Comments
|
• 100 MW plant in Spearville, KS
• Began construction in 2005
|
ü Completed in Q3 2006
ü In rate base from 1/1/2007
ü No regulatory disallowance
|
|
• Selective Catalytic Reduction (SCR) unit at LaCygne 1
|
ü Completed in Q2 2007
ü In rate base from 1/1/2008
ü No regulatory disallowance
|
|
• Air Quality Control System at Iatan 1
|
üCompleted in Q2 2009
üIncluded in KCP&L KS, KCP&L MO and GMO rate base
with minimal disallowance
|
|
• Construction of Iatan 2 super-critical coal plant (850 MW;
73% GXP ownership share)1 |
ü In-service on 8/26/2010; Included in KCP&L KS, KCP&L MO
and GMO rate base with minimal (1%) disallowance |
|
Great Plains Energy effectively executed all elements of its Comprehensive Energy Plan and
received constructive regulatory treatment |
Rate Case Outcomes
|
||||||
Rate Jurisdiction
|
Initial Request
|
Amount
Approved |
Effective Date
|
Rate Base
|
Return on Equity
|
Rate-making
Equity Ratio |
KCP&L - Missouri
|
$55.8
|
$50.6
|
1/1/2007
|
$1,270
|
11.25%
|
53.69%
|
KCP&L - Missouri
|
$45.4
|
$35.3
|
1/1/2008
|
$1,298
|
10.75%
|
57.62%
|
KCP&L - Missouri
|
$101.5
|
$95.0
|
9/1/2009
|
$1,4961
|
n/a4
|
46.63%
|
KCP&L - Missouri
|
$92.1
|
$34.8
|
5/4/2011
|
$2,036
|
10.00%
|
46.30%
|
KCP&L - Kansas
|
$42.3
|
$29.0
|
1/1/2007
|
$1,0001
|
n/a2
|
n/a
|
KCP&L - Kansas
|
$47.1
|
$28.0
|
1/1/2008
|
$1,1001
|
n/a3
|
n/a
|
KCP&L - Kansas
|
$71.6
|
$59.0
|
8/1/2009
|
$1,2701
|
n/a4
|
50.75%
|
KCP&L - Kansas
|
$55.2
|
$22.0
|
12/1/2010
|
$1,781
|
10.00%
|
49.66%
|
GMO - MPS
|
$94.5
|
$45.2
|
6/1/2007
|
$918
|
10.25%
|
48.17%
|
GMO - MPS
|
$66.0
|
$48.0
|
9/1/2009
|
$1,1881
|
n/a5
|
45.95%
|
GMO - MPS
|
$75.8
|
$30.1
|
6/4/2011
|
$1,336
|
10.00%
|
46.58%
|
GMO - L&P
|
$24.4
|
$13.6
|
6/1/2007
|
$186
|
10.25%
|
48.17%
|
GMO - L&P
|
$17.1
|
$15.0
|
9/1/2009
|
$2861
|
n/a5
|
45.95%
|
GMO - L&P
|
$22.1
|
$29.3
|
6/4/2011
|
$422
|
10.00%
|
46.58%
|
Coal Unit
|
MW
|
SCR
|
Scrubber
|
Bag
House |
Other
Particulate Control (f) |
Mercury
Controls |
Cooling
Tower |
Iatan 1
|
621(a)
|
|
|
|
|
|
|
Iatan 2
|
618(a)
|
|
|
|
|
|
|
LaCygne 1
|
368(a)
|
|
|
|
|
||
LaCygne 2
|
341(a)
|
|
|
|
|
|
|
Hawthorn 5
|
563
|
|
|
|
|
|
|
Sibley 1 and 2
|
102
|
|
|
|
|
|
|
Sibley 3
|
364
|
|
|
|
|
|
|
Montrose 1, 2 and 3
|
510
|
|
|
|
|
|
|
Lake Road 4
|
99
|
|
|
|
|
|
|
Jeffrey Energy Center 1, 2 and 3
|
173(a)
|
|
|
|
|
|
|
If a scrubber is installed on both LaCygne 2 and Sibley 3, roughly 81 percent of the installed coal capacity would
have scrubbers
|
Coal Unit
|
MW
|
SCR
|
Scrubber
|
Bag House
|
Other
Particulate
Control
|
Mercury
Controls |
Cooling
Tower |
LaCygne 1
|
368(a)
|
|
|
|
|
|
|
LaCygne 2
|
341(a)
|
|
|
|
|
|
|
Retail MWh Sales and Customer Growth Rates
|
||||
1Q 2011 Compared to 1Q 2010
|
||||
|
|
Weather-Normalized
|
||
|
Total
Change in MWh Sales |
Customers
|
Use / Customers
|
Change MWh Sales
|
Residential
|
(4.0%)
|
(0.1%)
|
(5.7%)
|
(5.8%)
|
Commercial
|
(1.3%)
|
0.3%
|
(2.0%)
|
(1.7%)
|
Industrial
|
(0.0%)
|
(0.9%)
|
1.1%
|
0.1%
|
|
(2.2%)
|
0.0%*
|
(3.1%)*
|
(3.2%)*
|
|
Earnings (in Millions)
|
|
Earnings per Share
|
||
|
2011
|
2010
|
|
2011
|
2010
|
Electric Utility
|
$ 7.0
|
$ 24.9
|
|
$ 0.05
|
$ 0.18
|
Other
|
(4.7)
|
(4.6)
|
|
(0.04)
|
(0.03)
|
Net income
|
2.3
|
20.3
|
|
0.01
|
0.15
|
Less: Net loss attributable to noncontrolling interest
|
0.1
|
-
|
|
-
|
-
|
Net income attributable to Great Plains Energy
|
2.4
|
20.3
|
|
0.01
|
0.15
|
Preferred dividends
|
(0.4)
|
(0.4)
|
|
-
|
-
|
Earnings available for common shareholders
|
$ 2.0
|
$ 19.9
|
|
$ 0.01
|
$ 0.15
|
Great Plains Energy Debt
|
||||||||
($ in millions)
|
KCP&L
|
GMO (1)
|
GPE
|
Consolidated
|
||||
|
Amount
|
Rate (2)
|
Amount
|
Rate (2)
|
Amount
|
Rate (2)
|
Amount
|
Rate
(2) |
Short-term debt
|
$ 383.8
|
0.61%
|
$ 205.0
|
3.06%
|
$ 14.0
|
3.06%
|
$ 602.8
|
1.50%
|
Long-term debt (3)
|
1,780.1
|
6.13%
|
863.9
|
10.20%
|
637.0
|
7.57%
|
3,281.0
|
7.45%
|
Total
|
$2,163.9
|
5.15%
|
$1,068.9
|
8.78%
|
$ 651.0
|
7.47%
|
$3,883.8
|
6.51%
|
|
|
|
|
Generating
Facilities (excl. Iatan 2) |
172.2
|
174.6
|
171.8
|
Transmission &
Distribution |
171.0
|
178.9
|
232.2
|
General
Facilities |
29.2
|
63.2
|
44.6
|
Nuclear Fuel
|
14.8
|
26.2
|
31.5
|
Environmental
|
63.0
|
171.0
|
219.1
|
Iatan No. 2
|
53.1
|
-
|
-
|
(millions)
|
Three Months Ended March 31
|
|
|
2011
|
2010
|
Operating revenues
|
$ 492.9
|
$ 506.9
|
Fuel
|
(104.9)
|
(101.8)
|
Purchase power
|
(54.9)
|
(65.5)
|
Transmission of electricity by others
|
(7.5)
|
(5.6)
|
Gross margin
|
$ 325.6
|
$ 334.0
|